High-rise construction, core first, floor by floor.

Towers planned around the core, the crane and a repeatable floor cycle.

Send drawings and BOQ

How we build it

August Tower, Bramha Corp., Wadgaon Sheri, Pune
  1. Raft and crane

    Raft cast, crane erected

  2. Core leads

    Lift and stair core climbs first

  3. Floor cycle

    One Mivan cycle per floor

  4. Survey and top out

    Plumb checked every floor

What the scope covers

Core-led tower sequencing
Lift and stair cores lead the floor cycle
Floor-cycle planning on Mivan
Repeatable floor cycles on aluminium formwork
Tower-crane logistics and lifts
Crane and lift plan fixed before mobilisation
Concrete pumping at height
Pump lines and pours planned floor by floor
Line, level and verticality survey
Checked at every floor before the next pour

Owned for this work

2 × 50 m ACE TC5034 tower cranes, 36 m ACE MTC3625 movable tower crane and 5 concrete lifts.

See the full fleet

A programme that is computed.

Casting sequences, pour milestones and critical path computed with AI, re-sequenced as site data comes in.

  1. 1stExecution targets issued to every sitePlanning engineer
  2. 15thClient RA bills submitted, strictlyBilling
  3. 25thHiring for next month closedHR
  4. 27–28thNext month’s plan draftedPlanning engineer
  5. 30thPlan frozen against billing targetsDirectors

Questions

Short answers on scope, plant and pricing for this work.

Talk to Rajat Kate, +91 77438 51234How we run every site
How do you build high-rise towers?

We plan every tower around the core, the crane and a repeatable floor cycle. The raft is cast and the crane erected first. The lift and stair core then climbs ahead of the floors, and each floor runs one Mivan cycle. Line, level and verticality are surveyed at every floor before the next pour.

What cranes do you own?

We own two ACE TC5034 tower cranes with 50 m jibs and one ACE MTC3625 movable tower crane with a 36 m jib. We also run 5 concrete lifts and 2 Aquarius 1407D concrete pumps for pumping at height. The crane and lift plan is fixed before mobilisation.

Do you use Mivan formwork?

Yes, we own 3,600 m² of Mivan aluminium formwork for walls and columns. Columns, shear walls and lift cores are cast on Mivan or conventional forms, and towers run one Mivan cycle per floor. Our design analysis team checks Mivan fit, pour joints and sequence before drawings reach site.

How do you keep a high-rise programme on track?

We compute the programme. Casting sequences, pour milestones and the critical path are computed with AI and re-sequenced as site data comes in. Execution targets go to every site on the 1st, a DPR reaches you by 17:45 every working day, and the project manager reviews progress with you weekly.

Send your drawings and BOQ.

We’ll come back with a priced BOQ, a clear scope and a day-wise programme.

Email your drawings

Call +91 77438 51234WhatsApp